Expressway project decision to affect 96 homes



The environmental Record of Decision (ROD) has been issued for the proposed 12.5-mile Southern Beltway Project from I-79 to the Mon/Fayette Expressway (Turnpike 43) at a new interchange south of Finleyville. The U.S. Army Corps of Engineers signed the ROD on May 13, which concludes the environmental decision-making process for the estimated $730 million project.

The corps' action formally designates the 12.5-mile Green Alternative Option 1A / Tan-Red Alternative, located exclusively in Washington County, as the selected alternative. Construction of this project would complete the Pennsylvania Turnpike Commission's (PTC) Southern Beltway system that begins at Route 60 and extends eastward to an interchange with Route 22 (opened to traffic 10/06), continues eastward with the proposed Route 22 to I-79 project (currently in final design), and concludes with the eastern end point of the I-79 to Mon/Fayette Expressway interchange with Turnpike 43 south of Finleyville.

"Having successfully completed the environmental process on this final Southern Beltway Project gives us an opportunity to create a 32-mile tolled expressway between the Pittsburgh International Airport and the Mon/Fayette Expressway and to establish an important transportation link to the airport corridor from key locations in Allegheny and Washington Counties," said Turnpike CEO Joe Brimmeier.

The selected alternative traverses Cecil, North Strabane, Peters, Nottingham and Union Townships.

It would cross over Little Chartiers Creek, a portion of Canonsburg Lake (a public recreation area owned by the PA Fish and Boat Commission), and Route 19 approximately 1,500 feet south of the intersection of Waterdam Road and Route 19. The Corps' ROD includes commitments to mitigate for unavoidable environmental impacts.



The bridge over Canonsburg Lake (approximately 53 feet high) would be designed to avoid direct impacts to fishing and boating areas.

Residential displacements associated with the selected alternative are estimated at 96. There are three estimated business displacements.

Between the western end point (I-79) and eastern endpoint (Turnpike 43), interchanges proposed include completion of the local interchange with SR 1089 (Morganza Road), and interchanges with Route 19 near Waterdam Plaza via a new connector road in North Strabane Township and with SR 1016 (Sugar Run Road) in Nottingham Township.

Securing this final ROD marks the end of a 17-year project development process that began in June of 1992 following Pennsylvania State legislative Acts 61 of 1985 and 26 of 1991 that mandated that the PTC study, design and construct what became four Mon/Fayette Expressway Projects and three Southern Beltway Projects in Allegheny, Washington and Fayette Counties.

Upon completion of Phase II of the Uniontown to Brownsville Area Project in 2012, three of the four Mon/Fayette Expressway Projects will be open to traffic. Additionally, a 4-mile section of the expressway in West Virginia is expected to open by December 2009 resulting in 60-miles of new expressway between I-68 in West Virginia and PA Route 51 in Jefferson Hills Borough in Southeastern Allegheny County.

Of the three Southern Beltway Projects, the six-mile long Findlay Connector was opened to traffic in October 2006. Route 22 to I -79 is in final design, and the environmental clearance process is now complete for the I-79 to the Mon/Fayette Expressway project.

Brimmeier added "We are very proud of the fact that we have been able to get all of these projects through the environmental process and construct the majority of them.

"It is unfortunate that because of funding shortages we will not be able to advance the I-79 to Mon/Fayette Expressway Project to final design at this time. However, the PTC remains committed to exploring all avenues of funding, including Public-Private Partnerships, to bring the remaining Mon/Fayette Expressway Project from Route. 51 to I-376, and the two Southern Beltway Projects from Route. 22 to I-79 and the I-79 to the Mon/Fayette Expressway to construction."





0 comments
All comments will be reviewed by administrators and posted to their respective articles within 24 hours. Comments deemed inappropriate will not be posted.
Subject:
Body:
Poster:
captcha 9cc58aca69c549c689c59d56a401662b
Enter text seen above:

Home

Click for Canonsburg, Pennsylvania Forecast


© 2010 Observer Publishing Company. All rights reserved.
This material may not be published, broadcast, rewritten or redistributed.
395 Valley Brook Road • McMurray, PA 15317
Phone (724) 941-7725 • Fax (724) 941-8685 • Classified Fax (724) 942-3923