Lebo high school change orders could spark litigation

Bookmark and Share
Make text smaller Make text larger

There were signs that certain change orders for Mt. Lebanon’s high school renovation project could trigger litigation at the May 13 school board discussion meeting. Of particular concern was a $75,000 item related to winterization performed by general contractor Nello Construction.


According to project manager Tom Berkebile, the change order involved costs associated with masonry work during the winter months. “Nello submitted a significant number of change orders early in the year,” he explained. “This was primarily based on the initial timetable when Nello put its costs together.” Berkebile added that he did not anticipate unforeseen costs on that scale in the future, despite the fact that some future work would be exposed to the elements during the winter.


“I cannot believe the contractor did not include any winterization costs for a four-year project,” said board member Dan Remely. He requested more detailed information about the change order or that it be removed from the agenda for the May 20 school board meeting.


The district’s solicitor, Tom Peterson, advised any detailed discussion regarding potential litigation or claims against contractors take place in executive session. He said approving change orders would not impact the district’s ability to seek redress in the future. “Approving these items settles the issue of payment by the district for work the contractor performed. It does not address the cause of any issues,” Peterson said.


To date the project has used around 24 percent of its contingency budget. Project manager Bekebile estimated about 50 percent of the work has been completed and 42 percent billed.


School board president Elaine Cappucci emphasized that project costs remained under control. She said the reason the public has seen so many change orders is because the administration is identifying specific items in the interest of transparency. Ordinarily a project of this magnitude would see fewer change orders but for larger dollar amounts, she explained.


Cappucci concluded, “in terms of changes made to the design during the project: work is done, the change orders come to us, we pay for the work. Any discussions regarding who is responsible are reserved for executive session as items for pending litigation.”



Bookmark and Share Make text smaller Make text larger

Comments

Published May 16, 2013 at 8:54 am (Updated May 16, 2013 at 8:54 am)

Lebo high school change orders could spark litigation

What you Need to Know
  • Please respect the use of this community forum and its users.
  • Any poster that insults,threatens or verbally abuses or another member,uses defamatory language,or deliberately disrupts discussions will be banned.
  • Users who violate the Terms of service or any commenting rules will be banned
  • Please stay on topic."Trolling" to incite emotional responses and disrupt conversations will be deleted
  • To understand further what is and isn't allowed and the actions we may take, please read our Terms of service
  • To report breaches of the Terms of service use the report abuse button

You must register, sign-in or Facebook Login Button to make a comment.


Most Popular
Tell us here at
The Almanac what
you think!
April
2014
Saturday
19
S M T W T F S
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3
May